Thames Valley diversion channel planting and maintenance programme
Funded: 4.2 million (Regional Infrastructure Fund)
Total cost: $7m
Project starts: January 2026
Project ends: 2026/27
Waikato Regional Council regularly reviews its flood schemes to ensure they are working as they should.
These reviews evaluate the integrity of our schemes’ assets and observed changes within the catchment to identify and inform recommended maintenance and improvement works.
This project is a result of a review of the 8.94-kilometre rightbank stopbank asset along the Piako River right bank between Ngātea and Pipiroa.
Stopbank instability has been an ongoing issue in the Hauraki Plains, as the area is largely built up of extensive soft marine sediments.
The review, undertaken in June 2024, identified the following.
- The Piako River has become slower moving due to channel modification when the Piako River flood scheme was built in the 1950s-60s. This has led to an accumulation of sediment in the river.
- Bed sediment buildup to date has increased water levels in the river. Peak tide levels have increased by an estimated 20-40mm.
- The river has widened in some locations, resulting in a loss of riverside berm.
- Inundation of the riverside berms is destabilising the stopbanks by causing erosion, with increased risk of stopbank collapse.
- The crest level of the stopbank has dropped in some locations due to uneven settlement, which has reduced the design freeboard.
Proposed works
The overall project objective is to address the identified deficiencies through a multiyear investment programme. This includes:
- raising stopbank crests to reinstate freeboard and provide flood protection from a 1% Annual Exceedance Probability (AEP) tidal surge event
- shifting some sections of stopbank away from the river’s edge to improve long term stability
- raising the riverside berm to reduce tidal inundation and stopbank instability and help avoid future stopbank shifts
- purchasing land as necessary to support the proposed upgrades, while also taking account of future climate scenarios and potential for further river changes.
The upgrade of the right bank stopbank will happen first, with investigation and design for this side of the river complete and stage 1 works procured, with a January 2026 start date.
The overall duration of the entire project (both sides) will be significantly influenced by available funding. With government co-funding, it is anticipated that the upgrade of the right bank stopbank will take four years, however, without co-funding it would have likely taken eight to 10 years. Upgrading the left hand stopbank will take similar timeframes. Co-funding of $4.2 million from the Crown’s Regional Infrastructure Fund has been secured to contribute 60 per cent towards costs of upgrading the rightbank stopbanks.
What's happening now?
The council will start enabling works from 19 January 2026 to prepare for stopbank and berm construction works on the right bank, which is planned to start in October 2026.
The enabling works, expected to be completed by the end of April, include relocating boundary fencing and stopbank toe drains, removing obstacles such as stock fences and troughs, and constructing a haul road with drain crossings (installing culverts) to protect existing infrastructure from heavy vehicle movements.
Cultural considerations
We have found no evidence of protected archaeological sites in the current designated area. However, a 1992 archaeological survey did record some Māori archaeological sites in the paddocks immediately east of the site. Relocation of the toe drain could conceivably uncover artefacts, and we have invited iwi to have observers on site during toe drain construction.